St. Joseph's Villa, Dundas Long Term Care Home - Air Handling Unit Upgrade and Retrofit
Federal contribution
$863,597
Federal share80%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 3, 2024
20242025
Built
Approved 18 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- St. Joseph's Health System - St. Joseph's Villa (Dundas) - St. Joseph's Villa, Dundas
- Construction start
- May 1, 2025(actual)
- Construction end
- Nov 14, 2025(actual)
Against the original forecast
- Construction start8 months lateforecast Sep 1, 2024
- Construction end7 weeks earlyforecast Dec 31, 2025
Also in Hamilton
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67940 in the federal list. How to read these figures.