Electrification of Transit Garage
Federal contribution
$240,000
Federal share40%
of $600.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 12, 2024
today
2024202620282030
BuiltForecast
Approved 6 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Cornwall
- Construction start
- Apr 1, 2028(forecast)
- Construction end
- Mar 31, 2030(forecast)
Also in Cornwall
- Cornwall Wastewater Treatment$18.5M
- Construction of Cornwall Multi Sport Facility$9.2M
- Replacement Conventional and Para Transit Buses$4.8M
- Construction of Salt Storage Facilities$1.9M
- Rehabilitation of Cast Iron Watermains on Water Street, Riverdale, and East End Neighbourhoods to improve structural and hydraulic performance.$1.7M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 68035 in the federal list. How to read these figures.