TMUC Carbon Footprint Reduction
Federal contribution
$478,833
Federal share79%
of $609.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 20, 2023
2022202320242025
Built
Approved 6 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Transcona Memorial United Church
- Construction start
- Jan 25, 2022(actual)
- Construction end
- Mar 2, 2025(actual)
Against the original forecast
- Construction start7 months earlyforecast Aug 18, 2022
- Construction end17 months lateforecast Sep 29, 2023
Also in Winnipeg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 68381 in the federal list. How to read these figures.