TMUC Carbon Footprint Reduction

Winnipeg, Manitoba

completeOtherGICB
Federal contribution
$478,833
Federal share79%

of $609.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 20, 2023
2022202320242025
Built

Approved 6 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Jan 25, 2022(actual)
Construction end
Mar 2, 2025(actual)

Against the original forecast

  • Construction start7 months earlyforecast Aug 18, 2022
  • Construction end17 months lateforecast Sep 29, 2023

Also in Winnipeg

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 68381 in the federal list. How to read these figures.