5projects·$1.8Mfederal of $2.7M eligible
Repair project of the 3rd floor of the Joseph-Anger Pavilion
$156.0KSaguenay · Ventilation
complete·approved 2021
Repairs to the administrative wing of the Centre d'études collégiales de Charlevoix
$368.2KLa Malbaie · Ventilation
complete·approved 2021
Replacement of the windows in the swimming pool corridor
$398.0KSaguenay · Education, Training and Childcare
complete·approved 2021
Relocation of psychosocial services of Cégep de Jonquière
$399.1KSaguenay · Ventilation
complete·approved 2022
Repair of concrete structural elements
$456.9KSaguenay · Education, Training and Childcare
complete·approved 2021
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Repair project of the 3rd floor of the Joseph-Anger Pavilion Cégep de Jonquière | Saguenay | Ventilation | complete | $156.0K | $339.4K | 2021 |
| Repairs to the administrative wing of the Centre d'études collégiales de Charlevoix Cégep de Jonquière | La Malbaie | Ventilation | complete | $368.2K | $460.3K | 2021 |
| Replacement of the windows in the swimming pool corridor Cégep de Jonquière | Saguenay | Education, Training and Childcare | complete | $398.0K | $760.9K | 2021 |
| Relocation of psychosocial services of Cégep de Jonquière Cégep de Jonquière | Saguenay | Ventilation | complete | $399.1K | $582.8K | 2022 |
| Repair of concrete structural elements Cégep de Jonquière | Saguenay | Education, Training and Childcare | complete | $456.9K | $571.2K | 2021 |