9projects·$2.8Mfederal of $6.7M eligible
Addition of Backflow Preventers at Fifth St. Sewage Pumping Station
$6.1KHearst · Wastewater
complete·approved 2018
Re-roofing of fifth Street Pumping Station Building
$6.4KHearst · Wastewater
complete·approved 2018
Installation of Ultraviolet (UV-254) technology to monitor the efficiency of the process removing organic matter at Hearst's Water Treatment Plant
$14.5KHearst · Drinking Water
complete·approved 2018
Replace three (3) low-lift pumps at the Hearst Water Treatment Plant with new energy efficient pumps equipped with Variable Frequency Drives
$32.5KHearst · Drinking Water
complete·approved 2018
Construction of New Receiving Bay
$80.0KHearst · Healthcare Infrastructure
complete·approved 2021
Upgrade 10th Street pumping station to prevent contamination of adjacent river
$92.5KHearst · Wastewater
complete·approved 2018
Remove accumulated sludge from Hearst Wastewater Treatment Lagoons (cell #1)
$109.8KHearst · Wastewater
complete·approved 2018
Rehabilitation of Hearst Drinking Water Plant Disinfection Reservoirs
$545.8KHearst · Drinking Water
complete·approved 2022
Rehabilitation and improvements to the Hearst Claude-Larose Recreation Centre
$1.9MHearst · Recreation
complete·approved 2021