Installation of Ultraviolet (UV-254) technology to monitor the efficiency of the process removing organic matter at Hearst's Water Treatment Plant

Hearst, Ontario

completeDrinking WaterCWWF
Federal contribution
$14,500
Federal share50%

of $29.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedMay 24, 2017
ApprovedMar 27, 2018
2018
Built

Approved 10 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 17, 2017(actual)
Construction end
Mar 16, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 5, 2017