Remove accumulated sludge from Hearst Wastewater Treatment Lagoons (cell #1)

Hearst, Ontario

completeWastewaterCWWF
Federal contribution
$109,845
Federal share50%

of $219.7K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 17, 2017
ApprovedMar 27, 2018
2018
Built

Approved 8 months after the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 17, 2017(actual)
Construction end
Nov 8, 2018(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 5, 2017