5projects·$4.8Mfederal of $7.1M eligible
Reconstruction of Nawash Unceded First Nation Roads and Culverts
$3.1MChippewas of Nawash Unceded First Nation≈ · Highways and Roads
underway·approved 2020
Nawash Native Child Welfare Building Retrofit
$1.2MChippewas of Nawash Unceded First Nation≈ · Other
underway·approved 2022
Water Treatment Plant Upgrade
$500.0KCape Croker · Drinking Water
complete·approved 2016
Replace 2 Turbidity meters, transfer switch and media, and Pump station (1 and 2) chlorine and electrical upgrades
$11.7KChippewas of Nawash Unceded First Nation≈ · Drinking Water
complete·approved 2017
Water System Upgrade/Rehabilitation consisting of: Upgrading of SCADA, Installation of Main Valves & Distribution Hydrants
$9.6KChippewas of Nawash Unceded First Nation≈ · Drinking Water
complete·approved 2018
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Reconstruction of Nawash Unceded First Nation Roads and Culverts Chippewas of Nawash Unceded First Nation | Chippewas of Nawash Unceded First Nation≈ | Highways and Roads | underway | $3.1M | $4.2M | 2020 |
| Nawash Native Child Welfare Building Retrofit Chippewas of Nawash Unceded First Nation | Chippewas of Nawash Unceded First Nation≈ | Other | underway | $1.2M | $1.2M | 2022 |
| Water Treatment Plant Upgrade Chippewas of Nawash Unceded First Nation | Cape Croker | Drinking Water | complete | $500.0K | $1.5M | 2016 |
| Replace 2 Turbidity meters, transfer switch and media, and Pump station (1 and 2) chlorine and electrical upgrades Chippewas of Nawash Unceded First Nation | Chippewas of Nawash Unceded First Nation≈ | Drinking Water | complete | $11.7K | $143.1K | 2017 |
| Water System Upgrade/Rehabilitation consisting of: Upgrading of SCADA, Installation of Main Valves & Distribution Hydrants Chippewas of Nawash Unceded First Nation | Chippewas of Nawash Unceded First Nation≈ | Drinking Water | complete | $9.6K | $22.5K | 2018 |