5projects·$659.5Kfederal of $2.1M eligible
Seawood Estates Sanitary Sewer Extension
$365.7KHunter River · Wastewater
complete·approved 2009
Seawood Estates Sewer Extension Phase 2
$124.3KHunter River · Wastewater
complete·approved 2005
Wastewater Treatment Facility Improvements
$79.8KHunter River · Wastewater
complete·approved 2009
Seawood Estates Sewer Extension Phase 3
$51.3KStanley Bridge · Wastewater
complete·approved 2006
Pumping Station Upgrades - Emergency Power - Cavendish Road PS9 & PS10
$38.4KHunter River · Wastewater
complete·approved 2013
| Project | Location | Category | Status | Federal | Total | Approved |
|---|---|---|---|---|---|---|
| Seawood Estates Sanitary Sewer Extension Resort Municipality of Hunter River | Hunter River | Wastewater | complete | $365.7K | $1.2M | 2009 |
| Seawood Estates Sewer Extension Phase 2 Resort Municipality of Hunter River | Hunter River | Wastewater | complete | $124.3K | $372.9K | 2005 |
| Wastewater Treatment Facility Improvements Resort Municipality of Hunter River | Hunter River | Wastewater | complete | $79.8K | $239.4K | 2009 |
| Seawood Estates Sewer Extension Phase 3 Resort Municipality of Hunter River | Stanley Bridge | Wastewater | complete | $51.3K | $155.8K | 2006 |
| Pumping Station Upgrades - Emergency Power - Cavendish Road PS9 & PS10 Resort Municipality of Hunter River | Hunter River | Wastewater | complete | $38.4K | $139.2K | 2013 |