Dawson City Recreation Centre Construction
Federal contribution
$7.9M
$7,925,000
Federal share75%
of $10.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 7, 2025
today
202620272028
BuiltForecast
Approved 5 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- City of Dawson
- Construction start
- Jul 22, 2025(actual)
- Construction end
- Jun 30, 2028(forecast)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2025