Dawson Water & Wastewater Upgrades Phase 2

Dawson City, Yukon

underwayWastewaterSCF
Federal contribution
$11.8M
$11,775,000
Federal share75%

of $15.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 10, 2018
today
2018202120242027
BuiltForecast

Approved 6 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Dawson
Construction start
Mar 15, 2019(actual)
Construction end
Oct 1, 2028(forecast)

Against the original forecast

  • Construction start4 months earlyforecast Jul 1, 2019