Dawson Water & Wastewater Upgrades Phase 2
Federal contribution
$11.8M
$11,775,000
Federal share75%
of $15.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2018
today
2018202120242027
BuiltForecast
Approved 6 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Dawson
- Construction start
- Mar 15, 2019(actual)
- Construction end
- Oct 1, 2028(forecast)
Against the original forecast
- Construction start4 months earlyforecast Jul 1, 2019
Also in Dawson City
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51926 in the federal list. How to read these figures.