Back to projects

Dawson Water Treatment Upgrades and Pumphouse Replacement

Dawson City, Yukon

completeDrinking WaterSCF
Federal contribution
$11.3M
$11,250,000
Federal share75%

of $15.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 2, 2018
2018201920202021
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Dawson
Construction start
May 1, 2018(actual)
Construction end
Dec 20, 2020(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2018
  • Construction end3 months earlyforecast Mar 31, 2021

Also in Dawson City

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51715 in the federal list. How to read these figures.