Dempster Fibre
Federal contribution
$29.0M
$28,975,055
Federal share37%
of $78.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 2, 2019
20202021202220232024
Built
Approved 8 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Yukon Ministry of Highways and Public Works
- Construction start
- May 7, 2021(actual)
- Construction end
- Sep 12, 2024(actual)
Against the original forecast
- Construction start14 months lateforecast Feb 29, 2020
- Construction end3 months earlyforecast Nov 30, 2024
Also in Dawson City
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52994 in the federal list. How to read these figures.