Dawson City Recreation Centre Planning

Dawson City, Yukon

completeCapacity BuildingRNIS
Federal contribution
$1.2M
$1,183,345
Federal share75%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 25, 2024
2025
Built

Approved 5 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
City of Dawson
Construction start
Jul 4, 2024(actual)
Construction end
Jul 22, 2025(actual)

Against the original forecast

  • Construction start2 months lateforecast May 1, 2024
  • Construction end3 weeks lateforecast Jun 30, 2025

Also in Dawson City

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. How to read these figures.