Trondëk Hwëchin Youth Centre
Federal contribution
$378,492
Federal share75%
of $504.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 24, 2020
2021
Built
Approved 7 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Trondëk Hwëchin First Nation
- Construction start
- Jun 1, 2020(actual)
- Construction end
- Nov 17, 2021(actual)
Against the original forecast
- Construction start7 months lateforecast Nov 1, 2019
- Construction end16 months lateforecast Jul 31, 2020
Also in Dawson City
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. How to read these figures.