Pelly Crossing Pool Facility
Federal contribution
$2.0M
$2,000,000
Federal share75%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 24, 2019
202020212022
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Government of Yukon
- Construction start
- Jun 30, 2021(actual)
- Construction end
- Oct 27, 2022(actual)
Against the original forecast
- Construction start7 months lateforecast Dec 11, 2020
- Construction end7 months lateforecast Mar 30, 2022