Pelly Crossing Pool Facility

Pelly Crossing, Yukon

completeRecreationCCRIS
Federal contribution
$2.0M
$2,000,000
Federal share75%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 24, 2019
202020212022
Built

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Government of Yukon
Construction start
Jun 30, 2021(actual)
Construction end
Oct 27, 2022(actual)

Against the original forecast

  • Construction start7 months lateforecast Dec 11, 2020
  • Construction end7 months lateforecast Mar 30, 2022