Purchases to support transit for Selkirk First Nation, Yukon.

Pelly Crossing, Yukon

completePublic TransitRTSF
Federal contribution
$216,824
Federal share100%

of $216.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 20, 2026
20252026
Built

Approved 17 months before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
Selkirk First Nation
Construction start
Feb 1, 2025(actual)
Construction end
Sep 26, 2025(actual)

Against the original forecast

  • Construction start11 months lateforecast Feb 28, 2024
  • Construction end14 months lateforecast Jul 31, 2024