Klondike Highway Drainage Improvements

Pelly Crossing, Yukon

completeHighways and RoadsSCF
Federal contribution
$272,183
Federal share75%

of $362.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2017
Built

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Government of Yukon
Construction start
Jul 1, 2017(actual)
Construction end
Sep 1, 2017(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2017
  • Construction end4 weeks earlyforecast Sep 30, 2017

Also in Pelly Crossing

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51310 in the federal list. How to read these figures.