Small Diameter Piped System

Pelly Crossing, Yukon

completeDrinking WaterMRIF
Federal contribution
$859,137
Federal share32%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 18, 2006
20072008200920102011
Built

Approved 3 months before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
First Nations of Selkirk
Construction start
Feb 2, 2007(actual)
Construction end
Feb 4, 2011(actual)

Against the original forecast

  • Construction start7 months lateforecast Jul 1, 2006
  • Construction end4.3 years lateforecast Oct 1, 2006