Upgrading of the Saugeen Shores water system
Federal contribution
$3.4M
$3,359,229
Federal share33%
of $10.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
2006200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Saugeen Shores
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Mar 31, 2009(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Jun 1, 2005
- Construction end2.2 years lateforecast Dec 31, 2006