Upgrading of the Saugeen Shores water system

Port Elgin, Ontario

completeDrinking WaterMRIF
Federal contribution
$3.4M
$3,359,229
Federal share33%

of $10.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
2006200720082009
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Saugeen Shores
Construction start
Apr 20, 2005(actual)
Construction end
Mar 31, 2009(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Jun 1, 2005
  • Construction end2.2 years lateforecast Dec 31, 2006