MacGregor Point Park Infrastructure Development
Federal contribution
$278,623
Federal share43%
of $645.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 12, 2010
2011
Built
Approved 6 weeks before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of Ontario
- Construction start
- Sep 7, 2010(actual)
- Construction end
- Aug 31, 2011(actual)
Against the original forecast
- Construction end4 weeks lateforecast Jul 31, 2011
Also in Port Elgin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39717 in the federal list. How to read these figures.