Schedule

Announced and approvedFeb 13, 2009
20102011
Built
Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Saugeen Shores
Construction start
Sep 1, 2009(actual)
Construction end
Dec 31, 2010(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2009
  • Construction end3 months lateforecast Sep 30, 2010