Construction of an Inlet Works Building and Septage Receiving Station
Federal contribution
$770,000
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Town of Saugeen Shores
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Dec 31, 2010(actual)
Against the original forecast
- Construction start4 months lateforecast May 1, 2009
- Construction end3 months lateforecast Sep 30, 2010
Also in Port Elgin
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24606 in the federal list. How to read these figures.