Back to projects

10th Concession Drainage and Storm Sewer Installation

Port Elgin, Ontario

completeWastewaterISF
Federal contribution
$403,333
Federal share33%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Saugeen Shores
Construction start
Sep 1, 2009(actual)
Construction end
Dec 31, 2009(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Sep 20, 2009
  • Construction end11 months earlyforecast Dec 1, 2010