10th Concession Drainage and Storm Sewer Installation
Federal contribution
$403,333
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Saugeen Shores
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Dec 31, 2009(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Sep 20, 2009
- Construction end11 months earlyforecast Dec 1, 2010
Also in Port Elgin