Replacement of three culverts
Federal contribution
$332,627
Federal share33%
of $997.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
20062007
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- County of Haliburton
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Mar 27, 2007(actual)
Against the original forecast
- Construction end3 months lateforecast Dec 31, 2006
Also in Minden Hills
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 11790 in the federal list. How to read these figures.