Construction of a pool
Federal contribution
$1.3M
$1,333,333
Federal share33%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 22, 2006
200720082009
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Shippagan
- Construction start
- Mar 17, 2006(actual)
- Construction end
- Jul 5, 2009(actual)
Against the original forecast
- Construction start2 weeks lateforecast Mar 1, 2006
- Construction end2.6 years lateforecast Nov 30, 2006
Also in Shippagan