Rehabilitation of the Sanitary Sewer

Shippagan, New Brunswick

completeWastewaterCC
Federal contribution
$378,227
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2009
2010
Built

Approved 4 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Shippagan
Construction start
Aug 10, 2009(actual)
Construction end
Sep 23, 2010(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 1, 2009
  • Construction end13 months lateforecast Aug 30, 2009