Rehabilitation of the Sanitary Sewer
Federal contribution
$378,227
Federal share33%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2009
2010
Built
Approved 4 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Shippagan
- Construction start
- Aug 10, 2009(actual)
- Construction end
- Sep 23, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2009
- Construction end13 months lateforecast Aug 30, 2009