Combined sewer separation
Federal contribution
$628,224
Federal share50%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 18, 2016
201720182019
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Shippagan
- Construction start
- Jun 19, 2017(actual)
- Construction end
- Sep 19, 2019(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 5, 2017
- Construction end23 months lateforecast Oct 31, 2017
Also in Shippagan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47340 in the federal list. How to read these figures.