Replacement of Sanitary Sewer and Construction Storm Water Sewer - 12th Street
Federal contribution
$377,066
Federal share50%
of $754.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
201720182019
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Shippagan
- Construction start
- Jul 24, 2017(actual)
- Construction end
- Sep 19, 2019(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 5, 2017
- Construction end2 weeks earlyforecast Oct 4, 2019
Also in Shippagan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48217 in the federal list. How to read these figures.