Back to projects

Replacement and rehabilitation of bridges and culverts

Ingersoll, Ontario

completeHighways and RoadsMRIF
Federal contribution
$14,382
Federal share33%

of $43.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 25, 2005
20062007200820092010
Built
Program
Municipal Rural Infrastructure Fund
Ultimate recipient
Town of Ingersoll
Construction start
Jun 15, 2005(actual)
Construction end
Jun 14, 2010(actual)

Against the original forecast

  • Construction end10 months earlyforecast Mar 31, 2011