Upgrading of the Goderich Wastewater System
Federal contribution
$1.2M
$1,151,167
Federal share33%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 25, 2005
20062007200820092010
Built
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- Town of Goderich
- Construction start
- Apr 20, 2005(actual)
- Construction end
- Feb 9, 2010(actual)
Against the original forecast
- Construction start11 months lateforecast May 6, 2004
- Construction end20 months lateforecast May 31, 2008