of $645.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Government of Ontario
Construction start
Oct 18, 2010(actual)
Construction end
May 31, 2011(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Sep 7, 2010