Reconstruction of County Rd. 30 (Patrick Street)
Federal contribution
$404,830
Federal share33%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- County of Huron
- Construction start
- May 22, 2009(actual)
- Construction end
- Aug 13, 2010(actual)