Replacement of interior lining and repair of the exterior of the Goderich Water Tower
Federal contribution
$210,950
Federal share50%
of $421.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
Approved 3 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Goderich
- Construction start
- Sep 1, 2017(actual)
- Construction end
- Nov 7, 2018(actual)
Against the original forecast
- Construction start5 months lateforecast Apr 1, 2017
- Construction end3 months lateforecast Jul 31, 2018
Also in Goderich
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48506 in the federal list. How to read these figures.