Purchase of accessible passenger vans to provide on-demand transportation in Humboldt, Saskatchewan
Federal contribution
$362,758
Federal share80%
of $453.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 27, 2024
2025
Built
Approved 8 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- City of Humboldt
- Construction start
- Feb 28, 2024(actual)
- Construction end
- Sep 30, 2025(actual)
Against the original forecast
- Construction start7 months lateforecast Aug 1, 2023
Also in Humboldt
- City of Humboldt - Wastewater Treatment System Upgrades$14.7M
- Water Distribution Plant and Reservoir$1.4M
- Uniplex and High School Retrofit$973.2K
- City of Humboldt Storm Water Detention Pond$647.1K
- Regional Authority of Carlton Trail Waste Management District (REACT) - Phase 2 Decommissioning of REACT Waste Management Facility$583.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 121696 in the federal list. How to read these figures.