Purchases to support transit for Athabasca, Alberta
Federal contribution
$101,084
Federal share79%
of $128.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 9, 2025
20252026
Built
Approved 13 months before the announcement.
- Program
- Permanent Public Transit Program
- Ultimate recipient
- Athabasca County
- Construction start
- Apr 1, 2025(actual)
- Construction end
- Mar 31, 2026(actual)
Against the original forecast
- Construction start13 months lateforecast Mar 1, 2024
Also in Athabasca
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 122229 in the federal list. How to read these figures.