Purchases to support transit for Athabasca, Alberta

Athabasca, Alberta

completePublic TransitRTSF
Federal contribution
$101,084
Federal share79%

of $128.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 9, 2025
20252026
Built

Approved 13 months before the announcement.

Program
Permanent Public Transit Program
Ultimate recipient
Athabasca County
Construction start
Apr 1, 2025(actual)
Construction end
Mar 31, 2026(actual)

Against the original forecast

  • Construction start13 months lateforecast Mar 1, 2024

Also in Athabasca

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 122229 in the federal list. How to read these figures.