Upgrading of the Wastewater Lagoon
Federal contribution
$553,668
Federal share33%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 9, 2009
ApprovedJul 23, 2010
20102011
Built
Approved 12 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Athabasca
- Construction start
- Aug 31, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Also in Athabasca
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28762 in the federal list. How to read these figures.