Athabasca Raw Water Intake Pump-House Modification

Athabasca, Alberta

completeDrinking WaterGIS
Federal contribution
$1.0M
$1,043,000
Federal share38%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 2, 2020
20212022
Built

Approved 3 months before the announcement.

Program
Green Infrastructure Stream
Construction start
May 17, 2021(actual)
Construction end
Jun 30, 2022(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 15, 2021

Also in Athabasca

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 56627 in the federal list. How to read these figures.