Peace River Trail Upgrades and Maintenance

Athabasca, Alberta

completeRecreationNRT
Federal contribution
$50,000
Federal share50%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 31, 2016
2016
Built

Approved 14 months before the announcement.

Program
National Recreational Trails Program
Construction start
Feb 1, 2015(actual)
Construction end
Nov 13, 2015(actual)