Water and Wastewater System Expansion
Federal contribution
$2.2M
$2,184,210
Federal share20%
of $10.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 2, 2005
200620072008
Built
Approved 6 weeks before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- City of Bathurst
- Construction start
- Jun 23, 2005(actual)
- Construction end
- Jun 20, 2008(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 1, 2005
- Construction end15 months lateforecast Mar 31, 2007
Also in Bathurst
- Bathurst - Water/Sewer renewal and Storm Separation Chaleur Street and St. Anne Street$2.1M
- Bathurst Regional Airport Expansion$1.9M
- Water Treatment Plant Expansion$1.3M
- Brideau Avenue - Water, Sanitary and Storm Systems Renewal$1.3M
- Allison Crescent - Water, Sanitary Sewer, Storm Infrastructure Renewals$961.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12312 in the federal list. How to read these figures.