Back to projects

Water and Wastewater System Expansion

Bathurst, New Brunswick

completeDrinking WaterMRIF
Federal contribution
$2.2M
$2,184,210
Federal share20%

of $10.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 2, 2005
200620072008
Built

Approved 6 weeks before the announcement.

Program
Municipal Rural Infrastructure Fund
Ultimate recipient
City of Bathurst
Construction start
Jun 23, 2005(actual)
Construction end
Jun 20, 2008(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2005
  • Construction end15 months lateforecast Mar 31, 2007

Also in Bathurst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 12312 in the federal list. How to read these figures.