Bathurst Regional Airport Expansion
Federal contribution
$1.9M
$1,856,759
Federal share30%
of $6.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 16, 2016
2017201820192020
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Northern New Brunswick Airport Authority
- Construction start
- May 1, 2017(actual)
- Construction end
- May 20, 2020(actual)
Against the original forecast
- Construction start13 months lateforecast Apr 1, 2016
- Construction end2.6 years lateforecast Oct 31, 2017
Also in Bathurst
- Water and Wastewater System Expansion$2.2M
- Bathurst - Water/Sewer renewal and Storm Separation Chaleur Street and St. Anne Street$2.1M
- Water Treatment Plant Expansion$1.3M
- Brideau Avenue - Water, Sanitary and Storm Systems Renewal$1.3M
- Allison Crescent - Water, Sanitary Sewer, Storm Infrastructure Renewals$961.8K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46426 in the federal list. How to read these figures.