Bathurst - Water/Sewer renewal and Storm Separation Chaleur Street and St. Anne Street

Bathurst, New Brunswick

underwayWastewaterGIS
Federal contribution
$2.1M
$2,120,000
Federal share40%

of $5.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 21, 2023
202420252026
BuiltForecast
Program
Green Infrastructure Stream
Ultimate recipient
City of Bathurst
Construction start
Jun 1, 2025(actual)
Construction end
Jul 1, 2026(forecast)

Also in Bathurst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67792 in the federal list. How to read these figures.