Back to projects

Water Treatment Plant Expansion

Bathurst, New Brunswick

completeDrinking WaterCC Top Up
Federal contribution
$1.3M
$1,294,043
Federal share33%

of $3.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 6, 2009
201020112012
Built

Approved 2 weeks before the announcement.

Program
Building Canada Fund - Communities Component Top Up
Ultimate recipient
City of Bathurst
Construction start
Oct 1, 2009(actual)
Construction end
May 31, 2012(actual)

Against the original forecast

  • Construction start2 months earlyforecast Dec 1, 2009
  • Construction end2 weeks lateforecast May 14, 2012

Also in Bathurst

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 27831 in the federal list. How to read these figures.