Back to projects

WTC Communication Center GHG Reduction & Energy Efficiency Upgrades

Westport, Ontario

approvedOtherGICB
Federal contribution
$2.0M
$2,000,000
Federal share64%

of $3.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 22, 2025
today
2026202720282029
BuiltForecast
Program
Green and Inclusive Community Buildings Program
Ultimate recipient
Village of Westport
Construction start
Jul 1, 2026(forecast)
Construction end
Dec 15, 2028(forecast)

Also in Westport