Closure of Waste Disposal Site
Federal contribution
$47,776
Federal share33%
of $143.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 5, 2009
2010
Built
- Program
- Building Canada Fund - Communities Component Top Up
- Ultimate recipient
- Village of Westport
- Construction start
- Jul 15, 2010(actual)
- Construction end
- Oct 27, 2010(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Aug 7, 2010
- Construction end4 weeks lateforecast Sep 30, 2010
Also in Westport
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 28015 in the federal list. How to read these figures.