Upgrades to the Westport Waterworks
Federal contribution
$50,502
Federal share33%
of $151.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 13, 2009
20102011
Built
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Village of Westport
- Construction start
- Apr 1, 2010(actual)
- Construction end
- Feb 15, 2011(actual)
Against the original forecast
- Construction start12 months lateforecast Apr 1, 2009
- Construction end4 months lateforecast Oct 31, 2010
Also in Westport
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 24585 in the federal list. How to read these figures.