Large Subsurface Disposal System (LSSDS) for the Village of Westport
Federal contribution
$1.4M
$1,450,000
Federal share50%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 1, 2017
20182019
Built
Approved 4 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Westport
- Construction start
- May 24, 2017(actual)
- Construction end
- Aug 31, 2019(actual)
Against the original forecast
- Construction start2 months earlyforecast Jul 24, 2017
Also in Westport
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51846 in the federal list. How to read these figures.