Energy renovation and remodelling of the old Presbytery
Federal contribution
$1.3M
$1,300,000
Federal share77%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 22, 2025
2026
BuiltForecast
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Municipality of Saint-Félix-de-Valois
- Construction start
- Jun 23, 2025(forecast)
- Construction end
- Feb 27, 2026(forecast)
Also in Saint-Félix-de-Valois
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 123803 in the federal list. How to read these figures.