Back to projects

Bring the water treatment plant up to code

Saint-Félix-de-Valois, Quebec

completeWastewaterCWWF
Federal contribution
$1.3M
$1,313,427
Federal share50%

of $2.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 28, 2017
20172018201920202021
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Aug 27, 2018(actual)
Construction end
Nov 10, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast May 15, 2018
  • Construction end6 weeks lateforecast Sep 30, 2020

Also in Saint-Félix-de-Valois

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48851 in the federal list. How to read these figures.