Construction of an indoor refrigerated ice rink
Federal contribution
$1.0M
$1,013,174
Federal share28%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 9, 2021
2021202220232024
Built
Approved 4 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Saint-Félix-de-Valois
- Construction start
- Jul 4, 2022(actual)
- Construction end
- Apr 4, 2024(actual)
Against the original forecast
- Construction end4 months lateforecast Nov 30, 2023
Also in Saint-Félix-de-Valois
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58088 in the federal list. How to read these figures.