New collection system and water supply in Belleville sector
Federal contribution
$398,371
Federal share40%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
2010201220142016
Built
Approved 6.5 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Municipality of Saint-Félix-De-Valois
- Construction start
- Sep 8, 2009(actual)
- Construction end
- Jul 31, 2012(actual)
Against the original forecast
- Construction end16 months lateforecast Mar 31, 2011
Also in Saint-Félix-de-Valois
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32705 in the federal list. How to read these figures.